Preliminary Project Timeline
Summer 2008
Project application submitted to the City of Sunnyvale. Planning Commission hearing and City Council meeting dates are yet to be determined.
Fall 2008
Project revisions — Abatement and demolition of clinic building at 301 Old San Francisco Road will take about two months.
2010
Total construction of the new medical center and parking structure will require one-and-a-half to two years to complete.
Summer 2010
Project completed (tentative).